The Project
As part of the construction of a new retail outlet, primary urbanisation works are planned.
The intervention involves:
- The resurfacing of existing flooring;
- The widening of the platforms and the reorganization of the sections with the insertion of a cycle track;
- The construction of a network for collecting rainwater affecting road platforms.
The following activities were conducted to achieve these objectives:
- acquisition of planimetric survey, inspection of existing networks and sub-services;
- tracing of a new road level with adjustment of the cross-sections and insertion of a cycle track alongside the carriageway and a mini roundabout to manage traffic entering/exiting the sales outlet;
- design of the new network for collecting rainwater affecting road platforms;
- hydraulic and static checks of the pipes.
Sectors
Details
-
LOCATION: Piossasco (TO)
-
STATUS: Concluded
Photogallery

Area dell’intervento per Nuova sede viabile per punto vendita IN’s

Area dell’intervento per Nuova sede viabile per punto vendita IN’s – estratto tavola di progetto
Project Sheet
-
CLIENT: IN's MARKET
-
SERVICES PERFORMED: Executive design
-
AMOUNT OF WORK: € 235.800
-
SURFACE: -
-